A new river bridge and cycle corridor · Tyneside

A third crossing, built in the open.

The Calloway Crossing Programme replaces a 1960s river bridge, adds a two-way cycle boulevard and builds a rail link to the new hospital campus. This site publishes the plan, the budget, the closures and the contractors, and updates the numbers every Friday.

The programme is funded by Tyneside Combined Authority and the national transport fund.

Bridge under construction with cranes working on the deck
The case

What the crossing is for

Three problems, each with a number attached, drive the design and decide the order of the work. The business case, traffic model and environmental statement are all published in full, so anyone can check the reasoning behind the plan.

Road crew spreading asphalt by hand

A bridge past its design life

Inspections found corrosion in 40 percent of the deck beams, and weight limits already stop buses crossing during storms. The new structure carries four lanes, a rail track and a pedestrian walkway for at least 120 years.

Urban boulevard with a red cycle lane and trees

Safer streets for riders and walkers

A protected boulevard with separated bike lanes links the university and the Quayside. Modelling expects 9,000 cycle trips a day within five years of opening.

Yellow tower cranes against a pale sky

Work planned around the river

Heavy lifts are scheduled for the six calmest months and every crane movement is published a week ahead. Neighbours see the sequence before the machines arrive.

Programme phases

Dates move when the river decides, and each change is listed on the updates page with the reason. A short written note explains whether it affects cost, safety or the opening date, and who approved the decision.

  1. Phase 1

    Utilities diverted and abutments built · Complete

    Gas, water and fibre mains were moved clear of the new foundations ahead of schedule.

  2. Phase 2

    Piers and steel deck · Under way

    Three river piers are finished and the first of nine deck segments is being lifted this season.

  3. Phase 3

    Rail link and station box · From next spring

    Tunnelling begins from the hospital campus towards the south bank.

  4. Phase 4

    Cycle boulevard and public realm · Final year

    Paving, trees and lighting are finished while traffic switches to the new bridge.

  5. Phase 5

    Old bridge removed and riverbank restored · After opening

    The 1960s structure is dismantled in sections, the abutments become viewing platforms and native reeds are replanted along both banks.

Delivery packages and who builds them

Two highway tunnel entrances cut into a rocky hillside
Tyne Heavy Civil JV

Bridge piers and steel deck

9 segments · 1,150 tonnes each

Structures

Railway track crossing a large green steel truss bridge
Northern Rail Partners

Hospital rail link and station

2.4 km of new track

Rail

Workers in gloves joining large yellow pipes with hydraulic equipment
Wear & Coast Utilities

Mains diversion and resilience

11 km of pipe relaid

Utilities

Where the money goes

Figures are in millions of pounds at 2026 prices and are reconciled to audited accounts each quarter.

Calloway Crossing programme budget Sort by column
Bridge structure212 £m118 £m46 %
Rail link and station148 £m21 £m32 %
Cycle boulevard and public realm52 £m6 £m11 %
Utilities diversion34 £m34 £m7 %
Contingency16 £m0 £m4 %

Progress this quarter

Structure complete
54%
People on site at peak
1,180
Contracts won by regional firms
38%
Lost-time injuries since January
0

Next milestone: the first deck segment is lifted

Heavy lift weekends are announced in advance and viewing points open to the public on the south bank path.

  1. --Days
  2. --Hours
  3. --Minutes
  4. --Seconds

 

Get lift alerts

Questions from neighbours

Will the river path stay open?

A temporary route is signed during lifts, and the main path reopens each evening once the crane is parked.

Will trees be removed?

Thirty-one trees on the north approach must go, and 140 native replacements will be planted along the boulevard, with species chosen by a panel of local gardeners and the council's arboriculture officer.

How loud will the work be?

Piling is limited to 8:00 to 18:00 on weekdays, and monitors report noise levels at three houses on the programme website.

Who pays for the project?

Capital funding comes from the national transport fund and the combined authority, with no new local tax. Every change to the budget above ten thousand pounds is reported to the scrutiny panel.

What happens to the old bridge?

It stays open until the new deck carries traffic, then it is dismantled over fourteen months. Steel is recycled and the stone abutments are kept as viewing platforms.

Will buses be disrupted?

Two weekend closures are planned for the final traffic switch. Operators will publish diversions a month ahead, and a temporary shuttle will run across the river meanwhile.

Who do I call about damage or dust?

Call the community line on the number below at any hour. Each report is logged, and a named liaison officer replies the next working day with what will be done.

Can I see the contracts?

Yes. Awarded contract summaries and the supplier list are published within 30 days of signature.

Receive weekly closure and progress notes

One email each Friday with closures, noisy works and any change to the programme dates. Residents within 500 metres also get a leaflet through the door, and businesses on the diversion routes receive a direct line to the traffic manager.

We use your address for project notices only. Call +44 191 496 0142 for a paper copy.